Update on Main Street Road Works from Bray Town Council:
After several meetings in recent days with the engineers, contractors, the liaison committee and Bray Chamber it is envisaged that the heavy street works have been delayed by 8 weeks. This delay has occurred because of difficulties in pipe laying of the storm drains and connection complexities between existing services at cross sections.
The contractor has agreed to extend the working hours and engage a second crew to excavate and lay the new paving. The west side up as far as Kevin’s Square will be completed towards the end of next week and then the two crews will then operate on the east side simultaneously. The contractor hopes to have both sections up to Novara Road completed by late November when he will stop all works for a period of 4 to 6 weeks to facilitate the proposed Christmas Festival.…